Milton E. Proby Construction Update
Construction Activities for August 2011
-
Continue with irrigation and seeding throughout the project
-
Continue with asphalt paving
-
Curb and Gutter work throughout the project
- Continue storm sewer pipe installation
-
Finish MSE Walls on the Academy Bridge and the Ramp C bridge
- Continue Hancock Expressway reconstruction
- Relocate utilities on Drennan Road
-
Begin water line work on Drennan Road
- Install light poles
- Relocate the Academy Boulevard Bus Stop
- Building the new exit from the Colony Hills Apartment Complex