Sign up for email alerts.
Enter a valid email address:

 

 


Join The Conversation. Upcoming Events


 

 

Traffic Advisory:  Beginning at 7a.m. on July 26th the turn lane from eastbound Drennan Road merging onto southbound Academy will be closed .Click here to view the complete Advisory.

Milton E. Proby Construction Update  

Construction Activities for August 2011

  • Continue with irrigation and seeding throughout the project
  • Continue with asphalt paving
  • Curb and Gutter work throughout the project
  • Continue storm sewer pipe installation
  • Finish MSE Walls on the Academy Bridge and the Ramp C bridge
  • Continue Hancock Expressway reconstruction
  • Relocate utilities on Drennan Road
  • Begin water line work on Drennan Road
  • Install light poles
  • Relocate the Academy Boulevard Bus Stop
  • Building the new exit from the Colony Hills Apartment Complex