Traffic Advisory:  Beginning at 7a.m. on July 26th the turn lane from eastbound Drennan Road merging onto southbound Academy will be closed .Click here to view the complete Advisory.

 

Completed Spring 2011 Work:

Completed construction and opened Ramp A, Ramp B and Ramp C

Completed storm drain work to tie in and finish north and south Academy ponds

Finished gas and utility relocations on Drennan

Top-soiled and seeded most areas along the new roadways

Completed curb and gutter along Hancock Expressway

Finished the new entrance to the Drennan Road and Academy Boulevard Loaf & Jug

Installed cable rail in median of Proby Parkway at Charro Drive

Completed installation of new traffic signals at Hancock Expressway and Proby

 

Anticipated Summer 2011 Work:

Completion of storm drain work on Drennan

Completion of updated waterline work on Drennan Road

Paving and opening of Phase 1 Drennan Road work

North bound Academy curb line and paving to allow traffic shift for median work

Start new signal work at Drennan and Academy

Continue roadwork on Drennan west of Academy

Removal of old Drennan Road east of Hancock Expressway

Construction of 12 foot trail and tie in at Hancock Expressway

 

 

Click here for a complete projected Construction Schedule